Battery systems that store energy for the grid.
Battery storage projects help utilities and developers manage when energy gets used. We build battery systems from 10 megawatts (enough for a small community) up to 400 megawatts (enough for a small city). They can stand alone or pair with solar or wind. We also build the substation that connects the batteries to the grid — and bundling both saves months on the schedule.
- Setup type
- Standalone · Paired with solar/wind
- Size range
- 10 to 400 MW
- Storage duration
- 2 to 8 hours
- Grid connection
- 12.47 to 230 kV
Battery storage, standalone or paired with solar and wind.
- A
Standalone battery systems
Battery systems on dedicated sites, sized for the local grid. We handle the site work, foundations, equipment, connection substation, and turn-on.
- B
Batteries paired with solar or wind
Battery storage that shares a site with a solar farm or wind project. We coordinate with the renewable energy contractor so everything works together.
- C
Connection substations
Every battery project needs a substation to connect to the grid. We build these with the same crews and engineers that handle our utility substation work.
- D
Testing and turn-on
Testing at the manufacturer, testing on site, tax credit certification support, and the final turn-on. All on the developer’s schedule, not the equipment supplier’s.
How a project runs, step by step.
- 01
Site preparation
Clearing, grading, drainage, and pad construction for the battery enclosures, power conversion equipment, and transformers.
- 02
Foundations
Setting the foundations under each enclosure and equipment skid. Digging the cable trenches that will connect everything.
- 03
Equipment installation
Placing the battery enclosures, setting the inverters and transformers, pulling the DC and AC cables, and grounding everything properly.
- 04
Connection substation
Building the substation that ties the battery system to the utility grid. This happens in parallel with the battery pad work, not after.
- 05
Testing and turn-on
Factory testing, site testing, tax credit certification, controls integration, and final turn-on — coordinated with the battery manufacturer and the developer.
Real projects we have built.
Common questions.
Related areas of our work.
Substation
New substations, upgrades to existing ones, and additions to live yards. From the concrete foundations through the relays that protect the system, all done by our own crews. Our team provides full-service electrical substation engineering, construction, and restoration support for new developments and repurposed industrial sites.
Read moreTransmission
New construction, rebuilds, and upgrades on transmission lines from 69 kV to 500 kV. When an outage is not an option, our crews has knowledge and expertise in live-line / barehand construction and maintenance.
Read moreAI & Data Center Power
Substations, redundant power feeds, and the medium-voltage distribution that powers data center campuses. From 100 MW to 1,200 MW, with phased turn-on for early load.
Read moreHave a battery storage project to plan?
We respond within two business days. For emergency, federal, and large industrial work, within four hours.